Tonstad Vindpark is now in commercial operation

We are pleased to announce that Tonstad Vindpark completed its construction phase and started commercial operation on 29 July 2020.

Read more

Six turbines in Tonstad wind farm have now begun to produce electricity

The first six (of 51) turbines in Tonstad wind farm are now producing energy. The assembly and electrification of the remaining turbines is ongoing.

Read more

Two turbines in Tonstad Wind farm have now begun to produce electricity

Two turbines in Tonstad Wind farm have now begun to produce electricity. Average production per turbine will be approximately 12GWh per year.

Read more

Electrification of the substation

The substation and the 132kV line in Tonstad Vindpark have been electrified.

Read more

Photos from assembly of the first turbine

The assembly of the first wind turbine of Tonstad Vindpark has begun.

Read more

Visit to the site for the installation of the first turbine

CFO Terje Kulseng, Head of communications Henriette Sarah Holberg and and Site manager Daniel Villanueva during the installation of the first turbine of Tonstad Vindpark.

Read more

One of three blades has been mounted on the first turbine

Recent photos from the installation of the first turbine are now available in the photo archive.

Read more

See updated photos of the transport in the photo archive

New photos from the transportation of the blades are now available for viewing in the photo archive. The most recent photographs are from the bridge between Kvinlog and the Stakkeland hills.

Read more

Drone footage of the first blade transport

Simen Haughom of Spectacular Norway filmed the transportation of the first blade with a drone.See the footage here.

Read more

The transportation of the first three blades was done successfully

The first three blades were transported in the night between Thursday 27th June and Friday 28th June. The installation of the first turbine began the same day.

Read more