We are pleased to announce that Tonstad Vindpark completed its construction phase and started commercial operation on 29 July 2020.
The first six (of 51) turbines in Tonstad wind farm are now producing energy. The assembly and electrification of the remaining turbines is ongoing.
Two turbines in Tonstad Wind farm have now begun to produce electricity. Average production per turbine will be approximately 12GWh per year.
The substation and the 132kV line in Tonstad Vindpark have been electrified.
The assembly of the first wind turbine of Tonstad Vindpark has begun.
CFO Terje Kulseng, Head of communications Henriette Sarah Holberg and and Site manager Daniel Villanueva during the installation of the first turbine of Tonstad Vindpark.
Recent photos from the installation of the first turbine are now available in the photo archive.
New photos from the transportation of the blades are now available for viewing in the photo archive. The most recent photographs are from the bridge between Kvinlog and the Stakkeland hills.
Simen Haughom of Spectacular Norway filmed the transportation of the first blade with a drone.See the footage here.
The first three blades were transported in the night between Thursday 27th June and Friday 28th June. The installation of the first turbine began the same day.